Day 13 - January 9, 2010 - FULL SPEED AHEAD!

After taking a break for two Saturdays during the holidays we had 9 team members at this weeks work session and they jumped right back into work.

The two teams working on the wings jumped right in and took both wings from a pile of parts, to being just about ready to begin installing skins.





A third team is working on the flaperons and now has all parts prepared and deburred and the few parts that need to be made from raw stock are completed. Assembly should be well under way by the end of our next session.

Assembly work has begun on the fuselage by the forth team. They completed the drilling work on the main center section bulkhead.