Day 14- January 16, 2010

We had 9 Team Members present for our work session this week. Work continued on the Fuselage, Flaperons and both Wings.


Both Flaperons are now very close to having the skins installed on them. Assembly of the fuselage centersection was completed. Skins were clecoed onto the left and right Wing substructures and riveting has begun.


Because our TeenFlight Leader will be out of town next weekend our next work session wont be until January 30.

Day 13 - January 9, 2010 - FULL SPEED AHEAD!

After taking a break for two Saturdays during the holidays we had 9 team members at this weeks work session and they jumped right back into work.

The two teams working on the wings jumped right in and took both wings from a pile of parts, to being just about ready to begin installing skins.





A third team is working on the flaperons and now has all parts prepared and deburred and the few parts that need to be made from raw stock are completed. Assembly should be well under way by the end of our next session.

Assembly work has begun on the fuselage by the forth team. They completed the drilling work on the main center section bulkhead.