Day 37 - October 9, 2010


We had 5 Team Members at the start of our work session this week. We made some good progress toward completing the finish kit portion of the RV-12 project.

The fuselage wiring harness installation is finally competed except for the last couple of steps, which shouldn't take very long next week. This will allow us to get to work on the control system installation and initial fitting of the wings.


Additional progress was made on the canopy installation. We are wrapping up the final prep. work to be ready to do the fiberglass lay-up installation at the front of the canopy.



Day 36 - October 2, 2010

We had five team members at our work session this week.  Our work goal was to concentrate on completing the fuselage wiring harness installation so that we can begin making progress on installing the control system and fitting the wings.  Other than a couple of minor items, we reached that goal.  We also made progress on finishing the canopy installation. 

Day 35 - September 25, 2010

We had six Team Members at our work session this week. We completed the cowl installation and made more good progress on the canopy installation. We also made some additional progress on the fuselage wiring harness installation.  Stay tuned for photos!

WE'RE BACK!!! Day 34 - September 18, 2010

Our first work session after a summer break and we got off to a slow but steady start.

We only had two Team Members in attendance but we made some good progress on the engine cowling and the canopy installation.

The Avionics and Power Plant kits will be put on order during this next week in anticipation of us completing the finish kit work in the next few weeks.