Day 43 - November 20, 2010

With five Team Members at our work session this week, we made some good progress.

The landing gear section is now complete with the installation of the brake lines.
The empennage installation will be complete, after the installation of the servo/control arm for the anti-servo tab.  We also made some good progress towards completing the Avionics Kit.
All of the engine preparation work is finished and it is ready to install on the fuselage, but we chose to delay that until completing the installation of the cooling radiator on the firewall.